JG Vertical was engaged to complete specialised facade remediation works on a commercial building in Crows Nest. During the initial investigation, our team identified additional defects within the external facade and recommended a revised remediation approach to ensure long-term structural protection and improved building presentation.

Scope of Work

Conducted facade inspections and defect investigations

Identified additional areas requiring remediation and repair

Developed a safe rope access methodology for external works

Planned works to minimise disruption within the live environment

Implemented specialised rope access systems for safe facade access

Coordinated remediation and protective coating works across the building exterior

JG Completed the Following

Applied protective coating systems to improve durability and finish.

Implemented rope access systems to safely access difficult elevations.

Completed external facade repairs and remediation works.

Carried out concrete patching and defect rectification to damaged areas.

Completed all works with minimal disruption to surrounding operations.

Delivered efficient, non-invasive access solutions without the need for scaffolding.

Improved the overall appearance and long-term protection of the building facade.